Test Grass Valley commissioning

  1. Rack, cable, and power on, using the K2 and GV STRATUS System Cabling Guide that shipped with the system.
  2. On a K2 Summit system, open K2 AppCenter and test basic record and play operations.
  3. From the control point PC, ping all K2 and GV STRATUS devices to test network connectivity. If the system has no control point PC, do this test from the GV STRATUS server.
  4. In the GV STRATUS application, do the following:
    1. In the Navigator, verify access to K2 Summit system bins.
    2. Create a Channel Panel and test record/play operations.
    3. In the Navigator, select assets on the K2 Summit system. The assets appear in the Asset List.
    4. Double-click an asset in the Asset List. The asset opens in the Inspector.
    5. In the Inspector, verify that the asset has a proxy association.
  5. In the Asset List, right-click the high-resolution asset and select Regenerate Proxy.
  6. Verify the following behavior:
    1. In the Inspector, the proxy association is momentarily not visible. This occurs as the GV STRATUS system deletes the proxy asset.
    2. In the Inspector, the proxy association becomes visible again. This occurs as a result of the GV STRATUS server that creates the proxy asset.
If tests succeed, the system is operating correctly, as it did when it left Grass Valley.